SPRINGFIELD, Vt. – The Edgar May Health and Recreation Center recently shared important updates and changes to the schedule and facility access during the scheduled demolition of the Foundry building annex.

Beginning Monday, Nov. 23, and continuing through Wednesday, Nov. 25, contractor EnviroVantage will begin demolition of the annex at the Clinton Street end of the building. To ensure everyone’s safety during this work, the accessible parking area on Clinton Street will be temporarily closed. Those with mobility issues can use the handicapped parking area on Bridge Street.
The walkway from Clinton Street to the Edgar May will be closed. Members and visitors will need to access the facility by traveling behind the Foundry building to the main entrance. The Edgar May will remain open during its regular hours Nov. 23-25.
On Monday, Nov. 30, and Tuesday, Dec. 1, demolition will shift to the section of the annex closest to the river. For everyone’s safety, the Edgar May will be closed from 7 a.m. – 3:30 p.m. on both days. It anticipates reopening at 3:30 p.m. each day for normal evening operations.
The Edgar May anticipates returning to normal traffic flow, parking, and facility access on Wednesday, Dec. 2, and will communicate any changes to this schedule as the project progresses.
Throughout the demolition, EnviroVantage will have large trucks and heavy equipment entering and exiting the work area via Clinton Street. Please use extra caution when approaching the Edgar May, follow posted signage, and remain clear of designated construction areas.