I-91 Rockingham bridges update

I-91Williams River Bridge in Rockingham, Vt. Photo provided

 

ROCKINGHAM, Vt. – The following is the anticipated schedule of the construction to take place on the I-91 Rockingham Bridges #24S & 24N over the Williams River beginning January 3.

Weather permitting, motorists should expect the I-91 southbound travel lane only over the bridge to be closed from January 3until approximately January 12 to allow crews to drill test borings. The left (passing) lane will be open to thru traffic and motorists should have little to no delays.

It is anticipated that from January 12 to 24 the northbound travel lane will be closed along with the northbound Exit 6 on-ramp. Traffic will be detoured to Route 5 north to I-91 Exit 7 on-ramp.

Please note that these dates are subject to change due to weather/road conditions.

Motorists please use extreme caution as the safety of the workers along with themselves is of the utmost importance.

The Public Relations telephone number to call with any questions or concerns regarding this project is 802-862-6085 or 866-602-6868. Find updates/changes at: http://countonitinc.com/road-construction-updates/